Ennore SEZ Supercritical Thermal Power Project

Station Name

Ennore SEZ

Location

Kattupalli, Ponneri TK, Thiruvallur Dt.

Installed Capacity

2 X 660MW

Scheduled Date of Completion

Unit 1 - 31.08.2026
Unit 2 - 30.09.2026
NCTPS1

Power Evacuation

Ennore SEZ STPP - North Chennai (PS) Tx line, 400 KV, DC line and Ennore SEZ SCTPP-ETPS Expansion Project, 400 KV DC line – overall 78% works completed. Ennore SEZ STPP - North Chennai-II Tx line, 400 KV, DC line (start up power)- 90% works completed.

Station

Ennore SEZ Supercritical Thermal Power Project

Location

Kattupalli, Ponneri TK, Thiruvallur Dt.

Capacity

2 × 660 MW = 1320 MW

Announcement Year

2013

Project Cost

Rs. 18085.49 Cr

Value of award (Rs. in Crores)/Date (including/amendments)

Rs.9884.11

Zero Date/Period of Execution

27.09.2014 / 42 months

Scheduled Date Of Completion

U-I: 31.08.2026
U-II: 30.09.2026

EPC contractor / Funding agencies

M/s.BHEL
M/s.Power Finance Corporation (PFC)

Expenditure ( Rs.in Crs.)

Rs. 12499.74 Crores w.r.t Project cost
Rs.6682.57 Crores w.r.t Awarded cost

Physical Progress (%)

74.42%

Financial progress (in%)

69.11 % w.r.t Project cost
67.60 % w.r.t Awarded cost

Coal Linkage / FSA

Linkage committee recommended for Bridge linkage available from Coal India Ltd. till mine development by TNPGCL
NCTPS1NCTPS1
Thermal energy may be invisible, but its impact lights up every corner of our civilization
In the balance of power and the planet, gas-based thermal plants offer a lower-carbon bridge to the future
Smarter fuel use, stronger thermal efficiency
Upgraded plants, upgraded performance
Efficiency in every operation, power in every unit
Natural gas: a cleaner flame driving the engine of modern electricity

Explore Our Trusted Websites