எண்ணூர் SEZ அனல் மின் நிலைய திட்டம்

Station Name

Ennore SEZ

Location

Kattupalli, Ponneri TK, Thiruvallur Dt.

Installed Capacity

2 X 660MW

Scheduled Date of Completion

Unit 1 - 31.08.2026
Unit 2 - 30.09.2026
NCTPS1

Power Evacuation

Ennore SEZ STPP - North Chennai (PS) Tx line, 400 KV, DC line and Ennore SEZ SCTPP-ETPS Expansion Project, 400 KV DC line – overall 78% works completed. Ennore SEZ STPP - North Chennai-II Tx line, 400 KV, DC line (start up power)- 90% works completed.

Station

Ennore SEZ Supercritical Thermal Power Project

Location

Kattupalli, Ponneri TK, Thiruvallur Dt.

Capacity

2 × 660 MW = 1320 MW

Announcement Year

2013

Project Cost

Rs. 18085.49 Cr

Value of award (Rs. in Crores)/Date (including/amendments)

Rs.9884.11

Zero Date/Period of Execution

27.09.2014 / 42 months

Scheduled Date Of Completion

U-I: 31.08.2026
U-II: 30.09.2026

EPC contractor / Funding agencies

M/s.BHEL
M/s.Power Finance Corporation (PFC)

Expenditure ( Rs.in Crs.)

Rs. 12499.74 Crores w.r.t Project cost
Rs.6682.57 Crores w.r.t Awarded cost

Physical Progress (%)

74.42%

Financial progress (in%)

69.11 % w.r.t Project cost
67.60 % w.r.t Awarded cost

Coal Linkage / FSA

Linkage committee recommended for Bridge linkage available from Coal India Ltd. till mine development by TNPGCL
NCTPS1NCTPS1
வெப்ப ஆற்றல் கண்களுக்கு தெரியாததாக இருந்தாலும், அதன் தாக்கம் நம் நாகரிகத்தின் ஒவ்வொரு மூலையையும் பிரகாசமாக்குகிறது
ஆற்றலின் சமநிலையிலும், பூமியின் பாதுகாப்பிலும், எரிவாயு அடிப்படையிலான வெப்ப மின் நிலையங்கள் குறைந்த கார்பன் வெளியீட்டுடன் எதிர்காலத்திற்கான ஒரு பாலமாக செயல்படுகின்றன
சிறந்த எரிபொருள் பயன்பாடு, வலுவான வெப்ப திறன்
மேம்படுத்தப்பட்ட நிலையங்கள், மேம்படுத்தப்பட்ட செயல்திறன்
ஒவ்வொரு செயல்பாட்டிலும் திறன், ஒவ்வொரு அலகிலும் சக்தி
இயற்கை எரிவாயு: நவீன மின்சாரத்தின் இயந்திரத்தை இயக்கும் தூய்மையான தீக்கனல்

எங்கள் நம்பகமான இணையதளங்கள்