எண்ணூர் SEZ அனல் மின் நிலைய திட்டம்
Station Name
Ennore SEZLocation
Kattupalli, Ponneri TK, Thiruvallur Dt.Installed Capacity
2 X 660MWScheduled Date of Completion
Unit 1 - 31.08.2026Unit 2 - 30.09.2026

Power Evacuation
Ennore SEZ STPP - North Chennai (PS) Tx line, 400 KV, DC line and Ennore SEZ SCTPP-ETPS Expansion Project, 400 KV DC line – overall 78% works completed. Ennore SEZ STPP - North Chennai-II Tx line, 400 KV, DC line (start up power)- 90% works completed.Station
Ennore SEZ Supercritical Thermal Power ProjectLocation
Kattupalli, Ponneri TK, Thiruvallur Dt.Capacity
2 × 660 MW = 1320 MWAnnouncement Year
2013Project Cost
Rs. 18085.49 CrValue of award (Rs. in Crores)/Date (including/amendments)
Rs.9884.11Zero Date/Period of Execution
27.09.2014 / 42 monthsScheduled Date Of Completion
U-I: 31.08.2026U-II: 30.09.2026
EPC contractor / Funding agencies
M/s.BHELM/s.Power Finance Corporation (PFC)
Expenditure ( Rs.in Crs.)
Rs. 12499.74 Crores w.r.t Project costRs.6682.57 Crores w.r.t Awarded cost
Physical Progress (%)
74.42%Financial progress (in%)
69.11 % w.r.t Project cost67.60 % w.r.t Awarded cost
Coal Linkage / FSA
Linkage committee recommended for Bridge linkage available from Coal India Ltd. till mine development by TNPGCL