உப்பூர் அனல்மின் திட்டம்

Station Name

Uppur Supercritical Thermal Power Project

Location

Uppur, Ramanathapuram District, TamilNadu.

Installed Capacity

2 X 800MW

Scheduled Date of Completion

02.02.2021
NCTPS1

Power Evacuation

Proposed to evacuate the power through 765 kV lines to Virudhunagar 765 kV SS, which has been commissioned.

Major Issues

Steps were initiated to advance the Uppur Project through a Joint Venture with NTPC and NLC. However, both entities have opted not to proceed with its revival in JV mode due to the high cost of power generation. The possibility of utilizing the high-cost materials from the Uppur Project in the newly proposed thermal power plant at Tuticorin District is presently under examination.

Station

Uppur Supercritical Thermal Power Project

Location

Uppur, Ramanathapuram District, TamilNadu.

Capacity

2 × 800 MW = 1600 MW

Announcement Year

2010

Fundiing

BHEL (BTG)

Project cost (Rs. in Crores)

Rs. 12,778/-

Value of award (Rs. in Crores)/Date

BTG:Rs.5852 Crs M/s. BHEL on 27.02.2016 (Zero date 3.08.2017) BoP:Rs. 3647 Crs M/s RIL on 21.02.2018, Contract short closed on 24/12/2020. SWIO package: M/s L&T, Rs.1067 Crs. on 08.05.2018, PMC: 43.47crs. M/s TCE on 19.02.2019. Total EPC : 10567.14 Crs

Period Of Execution

BTG : 42 Months, BoP: 36 Months, BoP: 36 Months, SWIO: 36 Months.

Scheduled Date Of Completion /Extension of Time (EOT)

BTG: 02.02.2021. EOT without levy of LD approved from 03.02.2021 to the date of which TANGEDCO Board decision will be taken . Bop: 20-02-2021, SWIO: 07.05.2021.

Expected date of Completion

Work suspended from 18.03.2021 as per NGT (SZ) Judgement dated 17.03.2021. Stay granted by Honourable Supreme court on 01.07.2021 against NGT(SZ) order. Project put on hold.

Expenditure (Rs. in Crores)

Rs.12778 Crores w.r.t Project cost
Rs. 10610.61 Crores w.r.t Awarded cost

Physical Progress (%)

BTG: 56.28%,
BoP: 0.81%,
SWIO:56.35%,
Overall progress:37.81 %.

Financial Progress (%) * Due to Exchange rate variation, FP is above 90%

BTG: 48.22%,
BoP:0.39%,
SWIO:44.70%,
Overall progress: 31.01 %

Coal Supplies

Design Coal: 70% imported and 30% domestic

Coal Linkage

Under SHAKTI Policy 2017 of Union Govt.
NCTPS1NCTPS1
வெப்ப ஆற்றல் கண்களுக்கு தெரியாததாக இருந்தாலும், அதன் தாக்கம் நம் நாகரிகத்தின் ஒவ்வொரு மூலையையும் பிரகாசமாக்குகிறது
ஆற்றலின் சமநிலையிலும், பூமியின் பாதுகாப்பிலும், எரிவாயு அடிப்படையிலான வெப்ப மின் நிலையங்கள் குறைந்த கார்பன் வெளியீட்டுடன் எதிர்காலத்திற்கான ஒரு பாலமாக செயல்படுகின்றன
சிறந்த எரிபொருள் பயன்பாடு, வலுவான வெப்ப திறன்
மேம்படுத்தப்பட்ட நிலையங்கள், மேம்படுத்தப்பட்ட செயல்திறன்
ஒவ்வொரு செயல்பாட்டிலும் திறன், ஒவ்வொரு அலகிலும் சக்தி
இயற்கை எரிவாயு: நவீன மின்சாரத்தின் இயந்திரத்தை இயக்கும் தூய்மையான தீக்கனல்

எங்கள் நம்பகமான இணையதளங்கள்