ETPS Expansion Project
Station Name
ETPS Expansion ProjectLocation
Ennore, ChennaiInstalled Capacity
1 X 660MWScheduled Date of Completion
2022-2023
Remarks
A Miscellaneous petition has been filed before TNERC on 03.09.2025.TNERC issued order on 20.11.2025. Note approval accorded by Chairman / TNPGCL on 02.12.2025 for floating tender for the procurement of power from ETPS Expansion Project under PPP mode. Subsequently tender was published in Newspapers on 04.12.2025 & uploaded in the TCIL portal on 05.12.2025.Station
ETPS Expansion ProjectLocation
Ennore, ChennaiCapacity
1 × 660 MW = 660 MWAnnouncement Year
2012Department
EnergyFunding
PFCProject Cost
Rs.6380.81Value of award (in Rs.Crs.)
Rs.4442.75Work Commenced
YesDate of work Commencement
Site was handed over to M/s BGRESL on 23.06.2022.But, M/s. BGRESL carried out only some preliminary works.Physical Progress
18% (Work Done by Erstwhile contractor M/s.LITL)1% (M/s.BGRESL)
Expenditure ( Rs. in Crores)
Rs. 2871.38 crores including IDCFinancial progress (in%)
45%