NCTPP Stage– III
Station Name
NCTPP Stage– IIILocation
Athipattu , North ChennaiInstalled Capacity
1 X 800 MWScheduled Date of Completion
2019-2020
Remarks
For completing Balance BOP Works, work awarded to M/s.CREW on 21.07.2025. M/s.CREW commenced the works from 28.07.2025 and the work under progressStation
NCTPP Stage– IIILocation
Athipattu , North ChennaiCapacity
1 x 800MWAnnouncement Year
2010Department
EnergyFunding
RECEstimated cost (DPR Cost) (Rs.in Crores)
Rs. 8723 Revised Project Cost : Rs. 10158 crores +1128.40 crores (sanction expected) = 11286.40 croresValue of award (in Rs. crore)
BTG - Rs.2942.43 crores. – M/s. BHEL on 29.01.2016BOP - BOP contract awarded to M/s.BGRESL terminated and Balance BOP package awarded to M/s.CREW for Rs.956.26 Crs. on 21.07.25
FGD – Rs.615 crores. – M/s .BHEL on 22.02.2021
Date of work Commencement
BTG 29.01.2016BOP 28.10.2016
FGD 22.02.2021
Physical Progress (in%)
97 %Expenditure ( Rs.in Crores)
Rs.10429.43 Crores w.r.t Project costRs. 5820.02 Crores w.r.t Awarded cost
Financial progress (in%)
93.12% w.r.t Project cost78% w.r.t Awarded cost
Estimated date of completion
The Unit was Commissioned and inaugurated by CM/GOTN on 07.03.2024. The Unit was Synchronized through Coal firing on 17.03.2024, full load achieved on 27.6.2024. The Trial run operation of NCTPP-III was started on 20.03.2025 and successfully completed on 19.04.2025. The Unit synchronized on 08.12.2025.2019-2020
Apr 2019 – Oct 2019Oct 2019 – Mar 2020
2022-2023
Apr 2022 – Oct 2022Oct 2022 – Mar 2023
2023-2024
Apr 2023 – Sep 2023Sep 2023 – Mar 2024
2024-2025
Apr 2024 – Sep 2024Sep 2024 – Mar 2025
2025-2026
Oct 2025 – Mar 2026